所属地区: --
所属机构: --
抱歉,该信息暂无中文翻译信息,为您显示项目原文信息。
Published date: 17 February 2025
Open opportunity - This means that the contract is currently active, and the buying department is looking for potential suppliers to fulfil the contract.
Boiler installations - 42160000
Central-heating radiators and boilers and parts - 44620000
Boilers - 44621200
Boiler installation work - 45331110
England
£200,000 to £1,000,000
OLDH001-DN763815-85222899
17 February 2025
13 March 2025
12pm
21 July 2025
29 August 2025
Works
Open procedure (below threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements below the relevant contract value threshold.
Yes
No
The programme is composed of replacement of mechanical plant room for 6 schools.
The tender is broken down into following 6 Lots:
Boiler Replacement Programme for Schools(Oldham)-Lot 1 Stanley Road Primary
https://procontract.due-north.com/Advert?advertId=8b622a84-f4eb-ef11-8134-005056b64545
Project number on Proactis: DN763815
Boiler Replacement Programme for Schools(Oldham)-Lot 2 Springhead Infant & Nursery School
https://procontract.due-north.com/Advert?advertId=9674b308-f6eb-ef11-8134-005056b64545
Project number on Proactis: DN763831
Boiler Replacement Programme for Schools(Oldham)-Lot 3 Mills Hill Primary School
https://procontract.due-north.com/Advert?advertId=e4c75b44-fdeb-ef11-8134-005056b64545
Project number on Proactis: DN763832
Boiler Replacement Programme for Schools(Oldham)-Lot 4 Horton Mill Primary School
https://procontract.due-north.com/Advert?advertId=22f42e23-01ec-ef11-8134-005056b64545
Project number on Proactis: DN763833
Boiler Replacement Programme for Schools(Oldham)-Lot 5 Propps Hall Junior Infant and Nursery School
https://procontract.due-north.com/Advert?advertId=448bc8eb-01ec-ef11-8134-005056b64545
Project number on Proactis: DDN763834
Boiler Replacement Programme for Schools(Oldham)-Lot 6 Freizland Primary School
https://procontract.due-north.com/Advert?advertId=9132c2a6-02ec-ef11-8134-005056b64545
Project number on Proactis: DN763835
Each lot has its own Specification, Social Value, Pricing Schedule and Quality ITT questions and own sets of governance documentation.
Additional text
Works Information
This Works Information is applicable for as the Lots.
Bidders to advised to consider below information for the respective Lots which they are considering for submitting a bid.
• Replacement of mechanical plantroom as per Design Option B.
• The Agreement shall commence on the date it is made, which is specified at the head of the Agreement. The commencement date is flexible to allow for any necessary changes to be made to the pre-planned programme of Works.
• It is anticipated that the Contractor will undertake and complete the Works in their entirety over the school's summer 2025 holiday period. However, if at any time prior to the commencement of the pre-planned Works the boiler at the school fails or it requires urgent repair or maintenance works and it would not be economically viable to undertake such repairs or maintenance to the boiler, the Employer reserves the right to issue an instruction to the Contractor under the Agreement amending the pre-planned time period for the completion of the Works and to urgently bring forward the boiler replacement works (as per Design Option A).
• In its instruction, the Employer can require the Contractor to undertake and complete the boiler replacement at the school urgently in line with the Employer's Requirements (save as to delivery period). The Contractor shall not be permitted to amend the Contract Sum if the schedule of Works is amended to prioritise the boiler replacement element of the Works. The boiler replacement Works shall be carried out within the timescales reasonably calculated and specified by the Employer in the instruction. Where relevant, the payment schedule for the boiler replacement element of the Works to allow for payment to be made in line with the new delivery timescales. The amended payment schedule for the boiler replacement works will be as detailed in the instruction.
• If the boiler replacement works are conducted outside of the anticipated delivery period, the boiler replacement works must still be carried out in line with the Employer's instruction and the terms and conditions of the Agreement. All remaining elements of the Works forming the Employer's Requirements will be conducted in the originally pre-planned timescales unless other arrangements are confirmed under an instruction.
Each Lot is an independent Lot.
Follow the instructions given in the description or the more information section.
Sandeep Kapoor
1st Floor
Barn Street
Oldham
OL1 1LP
United Kingdom
+44 0
Is there anything wrong with this page?
本网站为您提供准确和及时的招投标信息,但招投标信息存在着变更的可能,请您务必在交易前向招标代理机构或招标人咨询投标详细要求,有关招标的具体要求及情况以招标代理机构或招标人的解释为准。
如果您对这篇招标信息有任何补充或修改建议,请告知我们。
上一篇:
จ้างซ่อมเครื่องเตรียมชิ้นเนื้ออัตโนมัติระบบปิด จำนวน 1 เครื่อง下一篇:
Cleaning Contract Bromyard Public Toilets猜你喜欢