Published date: 20 February 2025
Open opportunity - This means that the contract is currently active, and the buying department is looking for potential suppliers to fulfil the contract.
Watch this notice
Print this notice
Closing: 6 March 2025, 3pm
Contract summary
Industry
Construction work for oil and gas pipelines - 45231200
Construction work for gas pipelines - 45231220
Gas supply mains construction work - 45231221
Show additional CPV codes for this notice
Gas distribution ancillary work - 45231223
Location of contract
East of England
Value of contract
£870,000
Procurement reference
X395
Published date
20 February 2025
Closing date
6 March 2025
Closing time
3pm
Contract start date
6 May 2025
Contract end date
31 October 2025
Contract type
Works
Procedure type
Competitive quotation (below threshold)
What is a competitive quotation (below threshold)?
The buyer selects a group of potential suppliers to invite to tender.
This procedure can be used for procurements below the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Central Region - East - Woodbridge, Suffolk - LPG Network Replacement for 200 properties
Brief scope of works
This project entails the D&B of a replacement LPG network supplying 200 properties on the Woodbridge estate. The cttr will be responsible for creating a network design that meets current stds, incorporating recommendations from a DNV Technical Report.
To facilitate seamless construction and ongoing maintenance, the design must support a phased approach, allowing properties to transition from the existing LPG gas supplies to the new network in stages. Each property will have a ground-mounted meter installed, to allow for other utilities.
The contractor will handle all excavation/installation/testing of the LPG mains/service connections. Each segment of the network will undergo pressure testing in line with IGEM stds.
At completion, the cttr will restore affected sites, incl pathways and landscaping. Final inspection with stakeholders will verify compliance, and comprehensive O&M and as-built docs, including test certs, will be provided as part of the closeout process.
For Amey to accept any EoI it is ESSENTIAL that any subcontractor is:
• willing to act as Main Contractor (ESSENTIAL);
• a member of Constructionline at GOLD;
• capable of working in a BIM environment;
• compliant with DefStan 05-138
• willing to deliver Social Value to our Client.
DESIRABLE attributes of our Supply Chain:
• have a CSR policy;
• have a Bus Cont & Disaster Rec'y Plan
If successful the subcttr will need to pass a PQQ, sign up to Amey T&Cs, and meet the MoD Sec Reqts.
Expressions of Interest, BY EMAIL ONLY.
Procurement Documentation will follow separately via a link from Curtis Fitch.
Note 1: The bidder must quote for all aspects of the Works.
Note 2: Future works of a similar nature may be negotiated based upon submitted rates.
Note 3: Those making an EoI will be required to sign-up to our 'Sub-Contract Agreement' where 'Mini Competitions' or 'Call Offs' will be used to tender works/services.
Note 4: For complex projects such as External Wall Insulation installation, Structural works etc. it is a requirement that the bidder must (at Contract Award) carry Professional Indemnity Insurance cover of not less than £1,000,000.
Note 5: Those making an EoI will be assessed in accordance with the Public Contract Regulations 2015 i.e. Regulations 57, 58 and 60. Amey Defence Services expressly reserves the right to require those making an EoI to provide additional information supplementing or clarifying any of the information requested.
Note 6: Depending on Amey's annual spend with individual bidders you may be required to either have committed to the Science Based Targets Initiative (SBTi), set SBTi approved near-term targets, or Net Zero targets.
This opportunity is also advertised on Constructionline.
ADS does not bind itself to accept any tender and is not liable for any costs incurred by those expressing an interest or tendering for this opportunity.
How to apply
Follow the instructions given in the description or the more information section.